White Street, Kilmore — road upgrade

Category:
Roads and parking
Status:
Works underway
Location:
White St, Kilmore
Suburb:
Kilmore
Anticipated Completion Date:
31 January 2022

About the project

Stage 2 — road upgrade to White Street between Allen Street and Green Street.

Works include standardisation of road widths, intersection treatments and pedestrian improvements.

Cost

Project subject to successful Fixing Country Roads Grant $415,000.

Total project cost $872,000.